Hardware Milestones
- 5/96 HXDS Arrival
- 9/5/96 ACIS-2C Arrival
- 9/11/96 LETG Arrival
- 10/29/96 HETG Arrival
- 11/30/96 HRMA Arrival
- 3/10/97 HRC Arrival
- 4/14/97 ACIS Arrival
- 5/5/97 HRMA from XRCF to TRW
X-Ray Calibration and Rehearsal Dates
XRCF Hotline for status and schedule: 205-544-8221
- 8/13/96 - 8/23/96 HXDS Verification (TMA / TOGA / HXDS)
- 8/23/96 - 9/4/96 Phase 1 Calibration Rehearsal (TMA / TOGA / HXDS)
- 9/4/96 - 9/5/96 HXDS 50 degree checkout (TMA / TOGA / HXDS)
- 9/30/96 1500 - 10/7/96 1700 Phase 2 Calibration Rehearsal (TMA / TOGA
/ FAM / LASS-Z / ACIS-2C)
- 10/22/96 0700 CDT - 10/28/96 0700 HXDS Development Testing (TMA / TOGA
/ HXDS)
- 10/28/96 0700 CDT - 11/01/96 0700 HXDS Verification (TMA / TOGA / HXDS)
- 11/19/96 - 11/21/96 HRMA GSE Vacuum Checkout and HSI Flat Field Testing
(XHSS / HXDS) no x-ray optic!
- 12/19/96-12/24/96 Phase 1 Part 1 / Part C (HRMA / HETG & LETG /
HXDS)
- 12/30/96-01/24/97 Phase 1 Part 2 / Part D (HRMA / HETG & LETG /
HXDS)
- 01/28/97-02/11/97 Phase 1 Part 3 / Part E (HRMA / HETG & LETG /
HXDS)
- 02/20/97-03/10/97 Phase 2 Part 1 / Part F (HRMA / HETG & LETG /
FAM / LASS-Z / ACIS-2C)
- 03/15/97-04/12/97 Phase 2 Part 2/ Part G (HRMA / HETG & LETG /
FAM / LASS-Z / HRC / ACIS-2C)
- 04/17/97-04/26/97 Phase 2 Part 3/ Part H (HRMA / HETG & LETG /
FAM / LASS-Z / ACIS / HRC )
- 05/07/97-05/18/97 ACIS Flat Field Calibration (FAM / LASS-Z / ACIS)
4/13/97 - just got our password back, sorry about the hiatus.
Dates may be inaccurate or unofficial. Please send corrections
to Roger.
See homepage for more verbose discussion of scheduling issues,
when appropriate.
last updated 05/18/97.