CALIBRATION GROUP SAO PIPE & MSFC/XRCF
WORK PLAN
This site under construction.
$Id: pipe.html,v 1.5 1998/03/18 15:00:20 emk Exp $
- At SAO pipe
- FPC window transmission for all fpc windows, March 4-6, 1998 [Brad
Wargelin]As of Mar. 12, we measured the blocking fraction of the support wires
on the fpc_hn and fpc_x2 windows. Data quality was excellent and I get a preliminary
result of about 11% blockage vs. the nominal 10%. I still need to correct
for wire overlap, rounded corners, etc. Dick Goddard has also remeasured
the fpc_hn and fpc_x2 blocking plates and I will tie that all together
next week. measured the energy dependence of the wire blockage
at Ti-K, Al-K, and C-K--haven't had time to look closely at results. This
concludes FPC testing.
- SSD pileup measurements Mar 9-10, 1998 [Mike McDermott]
- At SAO
- Supervise optical aperture measurements Mar 9-13, 1998 [B. Wargelin]
- Installation & Testing of HXDS at XRCF
- Mike McDermott, Mar 23-27
- Ian Evans, Mar 30-Apr 3
- Shaun Serej, Mar 23-27
- Ed Kellogg, Apr 1-3.
Back to:
SAO AXAF Mission Support Home Page
Ed Kellogg